Bessemer Road Construction Schedule
Written by Jesse Baroka on September 15, 2021
BESSEMER – City of Bessemer Update. W Galena Street is getting curb and gutter, this will be completed by Wednesday evening. Grading will occur in these areas of W Galena, S State St., W Longyear, S Hematite Friday, and continue into next week for paving. N Mine St. and S Moore St. – curb and gutter will be completed Wednesday evening. Fine grading and paving to follow next week. E Longyear St. from Case to Peck will be getting curb and gutter this week. S Sophie St. all utility work is completed, and in reconstruction of road will begin this week and continue into next week. N Sophie St sewer installation will begin at the dead end and move south towards US 2. S Beecher St. from Longyear to Colby is getting new storm sewer installation. The alley between Clayberg and S Beecher St will be closed for sewer installation. Please use caution when grading and paving crews are in the area. Try to avoid these areas.